Control panel, PLC and gas detection questions, answered
Plain answers to what plant managers, engineers and contractors ask before they call. Find your role and start there.
Plant and maintenance managers
A machine is down, a controller is obsolete or a shutdown needs planning.
When should a relay logic panel be upgraded to a PLC?
Five signs a relay logic panel should be replaced with a PLC, and what to check before you commit to the upgrade.
Who can troubleshoot a PLC when the original programmer is gone?
You do not need the original programmer to fix a PLC-controlled machine. What a controls technician needs, and what usually causes the fault.
Can a PLC program be recovered without the original file?
How PLC programs are uploaded from a running controller, what gets lost without the original project file, and how to protect yourself.
Our PLC is obsolete. Do we have to replace the whole control system?
Your options when a PLC is obsolete: stocking spares, a phased migration or a full replacement, and how to decide between them.
How long will a control panel replacement shut down our line?
What determines shutdown time for a control panel replacement, and how to plan the changeover to keep a production line down as briefly as possible.
Engineers and purchasing
Specifying, approving and buying control panels.
Does a custom control panel need to be certified in Ontario?
Electrical equipment used in Ontario must be approved. How custom control panels meet that requirement through certification or field evaluation.
What affects the cost of a custom control panel?
The main factors that set the price of a custom control panel in Ontario, and what to send a panel builder for an accurate quote.
What should a control panel RFQ include?
A checklist for a control panel request for quotation, so every builder prices the same scope and you avoid change orders later.
What enclosure rating does a control panel need?
How to choose a control panel enclosure rating for indoor, dusty, outdoor and washdown areas, with a simple comparison of common types.
Machine builders and mechanical contractors
You need controls for equipment you build or install.
What is the difference between a panel builder and a system integrator?
Panel builders manufacture the hardware, system integrators make the whole system work. How to tell which one your project needs.
Should a machine builder outsource its control panels?
When it makes sense for OEMs and machine builders to outsource control panels, and what to put in place so every panel comes back the same.
What does a dust collector control panel need?
The functions a dust collector control panel usually needs, from fan starters and filter cleaning to interlocks and combustible dust considerations.
Gas detection and hazardous locations
Sites where gas, vapour or dust is part of the job.
What do you need to quote an explosion-proof control panel?
A checklist of the hazardous area details a panel builder needs before quoting an explosion-proof control panel in Canada.
Explosion-proof, purged or intrinsically safe: what is the difference?
A plain comparison of explosion-proof enclosures, purged panels and intrinsically safe circuits for hazardous location control systems.
Does our facility need a gas detection system?
Which facilities commonly use gas detection, the gases involved, and how to confirm whether detection is required at your site.
How should a gas alarm tie into ventilation and equipment shutdown?
How to plan alarm levels, ventilation, shutdown and sensor faults for a gas detection system using a simple cause and effect table.
How often should a fixed gas detector be calibrated?
What sets the calibration schedule for fixed gas detectors, the difference between a bump test and calibration, and what records to keep.
Water and process operators
Analyzers, sample lines and instruments.
Should analyzers go on a prebuilt panel or be installed piece by piece?
Why many plants mount analyzers, sample lines and valves on a prebuilt process panel, and when installing on site still makes sense.
How do we connect an analyzer or sensor to our existing PLC?
How analyzers and sensors connect to a PLC using 4-20 mA, relay contacts, Modbus or Ethernet, and what to check before adding one.
Don’t see your question?
Ask us. Send a photo or a few lines about the problem, and we respond within 24 hours.