The short answer
A good control panel RFQ includes the drawings or a functional description, supply voltage, enclosure type and location, approval requirements, preferred component brands, PLC and HMI platform, what testing and documents you expect, and the delivery date. The clearer the scope, the easier the quotes are to compare.

The checklist
- Drawings: schematics, single-line and panel layout, or a written sequence of operation
- Power: supply voltage, phase, available fault current and control voltage
- Loads: motor sizes and starter type, including drives or soft starters
- Enclosure: environmental rating, material, size limits and mounting
- Approval: how the panel must be certified
- Controls: PLC and HMI brand, and who writes the program
- Preferred vendors: approved manufacturers and acceptable substitutes
- Testing: whether a witnessed factory acceptance test is required
- Documents: as-built drawings, manuals and program backups
- Scope limits: delivery date, shipping, installation and commissioning
Where quotes usually end up different
Quotes often vary because of what one builder assumed and another did not. Programming, approval, spare capacity and site work are the items most likely to be left out. Ask each builder to list exclusions so you are comparing the same job.
General information only, not engineering or safety advice. Confirm requirements for your site with a qualified professional. See our legal disclaimer.